Reviewed and signed off by Lyman Marshall Surveyors, Director, Surveyor and RICS Registered Valuer at Lyman Marshall Chartered Surveyors. Published 10 November 2026 · Updated 10 November 2026
A licence to alter is usually treated as a legal formality: a short deed the solicitors swap while the shopfitters wait in the car park. That is the wrong way round. The wording matters, but the drawings and specification attached to the licence are what decide, years later, what the tenant has to put back and what the landlord can claim for.
This guide explains what a licence to alter under a commercial lease actually does, what the law says about a landlord refusing consent, and the technical detail a surveyor should settle before any fit-out work starts on site.
Quick answer: A licence to alter is the landlord’s formal written consent for a tenant to carry out specified works to leased commercial premises. It records exactly what is approved, the drawings and specification, how the works must be done, and whether the tenant must reinstate them at the end of the lease. It is separate from planning permission, building regulations approval and party wall procedures.
What a licence to alter actually is
Most commercial leases restrict what a tenant can do to the building. Typically, structural and external works are prohibited outright, while internal non-structural works are allowed with the landlord’s consent. The licence to alter is the document that gives that consent.
It is normally a deed between landlord and tenant, and sometimes a guarantor. It sits alongside the lease rather than changing it. A well-drafted licence will usually cover:
- A precise description of the approved works, cross-referenced to numbered drawings and a written specification.
- A timescale for starting and completing the works.
- Standards of workmanship, the contractors to be used and insurance during the works.
- Which statutory consents the tenant must obtain before starting.
- Whether the tenant must remove the works and reinstate the premises at the end of the term.
- Whether the works are to be disregarded at rent review.
- Payment of the landlord’s legal and surveyor’s costs.
The legal drafting is a job for solicitors. The practical question of whether the drawings are accurate, whether the building can take the works, and what “reinstatement” will physically mean is a surveying question. That is where most disputes start.
Can a landlord refuse a licence to alter?
It depends on how the alterations covenant in the lease is written. There are three broad types, and it is worth reading your lease to find out which you have before you design anything.
| Type of covenant | What it says | Can the landlord refuse? |
|---|---|---|
| Absolute | The tenant must not carry out the works at all. | Yes. The landlord can say no for any reason, or agree on whatever terms they choose. |
| Qualified | No works without the landlord’s consent. | Consent to improvements cannot be unreasonably withheld, by statute. |
| Fully qualified | No works without consent, such consent not to be unreasonably withheld. | Only on reasonable grounds. |
The statutory protection comes from the Landlord and Tenant Act 1927. Where a lease contains a covenant against making improvements without consent, section 19(2) deems that consent not to be unreasonably withheld, whatever the lease says to the contrary.
The same subsection lets the landlord attach conditions. It can require a reasonable sum for any damage to, or reduction in value of, the premises or neighbouring premises it owns. It can also recover legal and other expenses properly incurred. Where the improvement does not add to the letting value, it can require an undertaking to reinstate, if that is reasonable.
Two points catch tenants out. First, the statute only helps where the lease allows alterations with consent. If the covenant is absolute for a category of work, the tenant has no statutory route to force it through. Second, there is no statutory deadline for the landlord’s answer.
No statutory clock on alterations
Tenants often assume a landlord must respond “within a reasonable time”. That duty exists, but only for some applications. The Landlord and Tenant Act 1988 imposes it on applications to assign, underlet, charge or part with possession. Alterations are not on that list.
In practice, that means the programme for a fit-out should assume the licence will take weeks rather than days. A complete, well-evidenced application is the best way to shorten it. A vague one invites questions, and every round of questions costs time.

What a landlord’s surveyor checks before consenting
When we act for a landlord, the question is not simply “are these works acceptable?” It is “what will this building look like, and be worth, if the works go ahead, and what happens when the tenant leaves?” The review usually covers the following.
Structure and loading
Mezzanine floors, heavy racking, roof-mounted plant, safes and new openings in walls all put loads where the original design may not have expected them. Where the works touch the structure, the landlord should see calculations from a qualified engineer, not an assurance from the shopfitter.
Services and the rest of the building
In a multi-let building, a tenant’s new kitchen extract, air conditioning or sprinkler alteration can affect other occupiers. Riser capacity, fire compartmentation and access for maintenance all need checking.
Effect on value and future letting
Some alterations make a unit easier to re-let. Others make it harder, such as heavily cellular offices in a building the market wants open plan. This is where the reinstatement question is really decided.
The existing condition
If the lease has no record of the premises’ condition at the start, it is worth recording the area affected by the works before they begin. Without that, nobody can prove later what was there before.
What the tenant should prepare
A tenant who wants a quick licence should make the landlord’s job easy. That means a single application pack, rather than drawings arriving in instalments.
- Accurate existing plans. Proposals drawn over inaccurate base plans are the most common reason for queries. If the plans in the lease pack are decades old, get the space properly measured first.
- Proposed drawings and specification. Numbered, dated and specific about materials, fixings and finishes.
- Engineer’s calculations for anything touching the structure or adding load.
- A method statement and programme, including working hours, deliveries and protection of common parts.
- Contractor details and insurance.
- A list of the statutory consents the works need, and who is obtaining them.
It also pays to ask for the landlord’s position on reinstatement at the outset. If the tenant would rather leave a partition or mezzanine in place at lease end, that is far easier to negotiate now, while the landlord wants the letting to proceed, than in five years’ time.

Licence to alter, planning, building regulations and party walls
A licence to alter is private consent from the landlord under the lease. It is not a statutory approval, and it does not replace any of them. Works may need several separate consents, each from a different body.
| Consent | Who gives it | Typically needed for |
|---|---|---|
| Licence to alter | The landlord, under the lease | Any works the lease restricts, even minor internal ones |
| Planning permission | The local planning authority | External changes and some changes of use (listed buildings also need listed building consent) |
| Building regulations approval | Building control | Structural work, fire safety, drainage, new services and similar |
| Party wall procedures | Adjoining owners, by notice and agreement or award | Notifiable works to or near a party wall |
The party wall point is where people most often confuse the two. The Party Wall etc. Act 1996 deals with the relationship between neighbouring owners, and GOV.UK is clear that party wall agreements are different from planning permission or building regulations approval. It has nothing to do with the landlord-tenant relationship. A tenant cutting into a wall shared with the next-door building may need both a licence to alter and a party wall process. If that applies, our party wall surveyors can explain what is notifiable.
Why the licence matters most at the end of the lease
Here is the part most guides skip. A licence to alter is signed at the start of a fit-out, but it is read at the end of the lease.
When the term ends, the landlord’s surveyor will compare the premises with what the lease and any licences allow. If the licence clearly records the approved works and the reinstatement obligation, the question is straightforward. If there is no licence, or it approves “works substantially in accordance with the attached drawings” and nobody can find the drawings, the argument can become expensive for both sides.
Unauthorised works carry a particular risk for tenants. Alterations carried out without consent may be a breach of covenant in their own right. They also leave the tenant with no written agreement about reinstatement to rely on when it comes to dilapidations.
Our advice: keep a complete, signed copy of every licence, with the final drawings attached, alongside the lease. Ask for a record of the works as built, with photographs, when the fit-out finishes. It costs very little at the time and can save a great deal at lease end.
Tenants taking on a unit with works already in place should also ask for copies of any licences granted to the previous occupier. Those works may become the new tenant’s problem at the end of the new lease unless the paperwork says otherwise. A pre-lease building survey is the right point to pick that up, and our guide to what a commercial property survey includes explains what we look at.
How a surveyor helps either side
We act for landlords and tenants on commercial property across Lincoln, Lincolnshire and Nottinghamshire, as part of our commercial property survey and landlord and tenant work. On a licence to alter, that typically means:
- For landlords: reviewing the application, advising on structure, services and effect on value, proposing reasonable conditions, and inspecting the completed works.
- For tenants: checking the lease before design starts, preparing a complete application, negotiating reinstatement terms, and recording the premises before and after the works.
We do not draft the licence itself. That is for your solicitor, and we work alongside them so the technical schedule and the legal wording say the same thing.
Licence to alter: frequently asked questions
What is a licence to alter?
It is a formal document, usually a deed, in which a landlord gives a tenant consent to carry out specified alterations to leased premises. It records the approved works and drawings, how they must be carried out, and whether the tenant must remove them at the end of the lease.
Do I need a licence to alter for internal works?
Often, yes. Many commercial leases require landlord consent even for internal non-structural works such as partitions, and some allow only minor demountable partitioning without consent. Check the alterations clause in your lease before any work is designed or priced.
Who pays for a licence to alter?
The tenant usually does. The Landlord and Tenant Act 1927 allows a landlord to require payment of legal and other expenses properly incurred in connection with consent to improvements, which normally covers the landlord’s solicitor’s and surveyor’s fees.
Can a landlord refuse a licence to alter?
Where the lease prohibits the works absolutely, yes. Where it allows improvements with consent, the 1927 Act says consent cannot be unreasonably withheld, although the landlord can impose reasonable conditions, including in some cases an undertaking to reinstate.
Planning a fit-out or reviewing a tenant’s proposals?
Talk to Lyman Marshall Chartered Surveyors before the work is designed, not after it has started. We can review the lease position, the drawings and the reinstatement terms, and give you a clear fixed fee.
Contact our commercial team or call 01522 438989.